On the right here you can see some upstairs studwork looking into the bathroom from bedroom 3.
On the left here is bedroom 2. You can see the landing cupboard we have asked for and in the background there is a blank corridor that we have created that will eventually house the stairs leading up into the loft. That'll be a long way off though!
Next week we've got the windows and doors going in so we're really going to see some differences. There will be some replacement lintels and a bit of brickwork to get those guys in as planned! Hopefully the B&Q insulation delivery will have been made too. I got a great deal on 15 rolls of 14 metre squared 100mm thick insulation. It was half price, all that for the bargain price of approx £240. I think we might be looking at the water next week too, we'll have to dig a trench for that, all the way from the corner of the property, round the back of the house and into the kitchen.
Anyway, half a day off work tomorrow to have a big sort out of the next load of jobs with Tony. More news to follow...